A consortium made up of Marubeni (project integrator), the University of Tokyo (technical advisor), Mitsubishi, Mitsubishi Heavy Industries, Japan Marine United, Mitsui Engineering & Shipbuilding, Nippon Steel & Sumitomo Metal Corporation, Hitachi, Furukawa Electric, Shimizu, and Mizuho Information & Research have been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012.
At present, the laying of the extra-high voltage undersea cable and the dynamic cable at the testing area has been successfully completed.
Setting one 2MW downwind-type floating wind turbine, the world’s first 66kV floating power sub-station and the cables.
< 2MW downwind-type floating wind turbine and 66kV floating power sub-station >
< Undersea cables >
The following activities need to be completed to start operation of the power facilities.
Expected commencement of operation of the power facilities is November 2013, but the schedule will be changed depending on the meteorological and sea conditions.
Mid October | - Depression of 66kV floating power sub-station - Pre-use inspection |
Late October | - Power receiving of 2MW floating wind turbine and 66kV floating power sub-station from Tohoku Electric Power Co., Inc |
November | - Commencement of operation |